West Terra Phase 1 and 2

Name:  West Terra Phase 1 and 2
Location:  West Terra Lane from North Central to Hoff Road
Map:  
Contact Name:  Dan Buesse
Contact E-mail:  dbuesse@ofallon.mo.us
Contact Phone:  636-379-5492
Description:  Project will resurface and widen West Terra from North Central to Hoff Road order to add 5' shoulders on both sides of the road and includes a 4-foot bicycle path on both shoulders along with the addition of some turn lanes. This project will have outside funding from the County Road Board at a 90/10 split.

Status Reports


Date: 8/31/2010
Project Status: Easement acquisition and utility coordination continue.

Date: 8/17/2010
Project Status: Easement acquisition and utility coordination is on-going.

Date: 8/4/2010
Project Status: Utility coordination is underway. Easement acquisition is on-going. Plans will be finalized once easements have been wrapped up.

Date: 7/20/2010
Project Status: Easement acquisition letters were mailed out last week. Final plans are being prepared.

Date: 7/6/2010
Project Status: Preliminary plans were sent to utility companies. An open house meeting was held on June 30.

Date: 6/22/2010
Project Status: The development of plans continue. Preliminary plans will be sent to utility companies this week.

Date: 6/8/2010
Project Status: Work continues for development of the plans. An open house public meeting will be held on June 30 from 4 p.m. to 6 p.m. at City Hall. Anybody interested in the project should attend.

Date: 5/25/2010
Project Status: Preliminary plans were delivered on May 12.

Date: 5/11/2010
Project Status: Preliminary plans are expected to be delivered tomorrow.

Date: 4/27/2010
Project Status: 75% plans are due on May 12. The designer is working on these plans.

Date: 4/13/2010
Project Status: Concept plans have been reviewed and comments have been prepared. Plans were sent to utilities. Preliminary plan development is underway.

Date: 3/30/2010
Project Status: Concept plans were delivered on March 22. Plans have been reviewed and a meeting has been scheduled for March 31. Plans will be delivered to utilities on March 31.

Date: 3/17/2010
Project Status: Concept plans (30%) are scheduled to be delivered on March 22.

Date: 3/2/2010
Project Status: A plan development meeting is scheduled for March 8. Concept plans are scheduled to be delivered on March 22.

Date: 2/16/2010
Project Status: The majority of the surveying has been completed. Topographic drawing is being prepared and design will start soon.

Date: 2/2/2010
Project Status: CMT is continuing to work on surveying of the project.

Date: 1/19/2010
Project Status: The design agreement with Crawford, Murphy, & Tilly was approved by Council. Surveying work will start this week.

Date: 1/5/2010
Project Status: Engineering contract will go before Council at the January 14 meeting.

Date: 12/22/2009
Project Status: Contract/scope negotiations are underway with the engineering firm.

Date: 11/20/2009
Project Status: Discussed project with CMT (engineer) to resurrect for 2010.

Date: 9/29/2009
Project Status: Amendment has been drafted for the County Road Board to forward fund project to start design in 2010.