Date:
8/31/2010
Project Status:
Easement acquisition and utility coordination continue.
|
Date:
8/17/2010
Project Status:
Easement acquisition and utility coordination is on-going.
|
Date:
8/4/2010
Project Status:
Utility coordination is underway. Easement acquisition is on-going. Plans will be finalized once easements have been wrapped up.
|
Date:
7/20/2010
Project Status:
Easement acquisition letters were mailed out last week. Final plans are being prepared.
|
Date:
7/6/2010
Project Status:
Preliminary plans were sent to utility companies. An open house meeting was held on June 30.
|
Date:
6/22/2010
Project Status:
The development of plans continue. Preliminary plans will be sent to utility companies this week.
|
Date:
6/8/2010
Project Status:
Work continues for development of the plans. An open house public meeting will be held on June 30 from 4 p.m. to 6 p.m. at City Hall. Anybody interested in the project should attend.
|
Date:
5/25/2010
Project Status:
Preliminary plans were delivered on May 12.
|
Date:
5/11/2010
Project Status:
Preliminary plans are expected to be delivered tomorrow.
|
Date:
4/27/2010
Project Status:
75% plans are due on May 12. The designer is working on these plans.
|
Date:
4/13/2010
Project Status:
Concept plans have been reviewed and comments have been prepared. Plans were sent to utilities. Preliminary plan development is underway.
|
Date:
3/30/2010
Project Status:
Concept plans were delivered on March 22. Plans have been reviewed and a meeting has been scheduled for March 31. Plans will be delivered to utilities on March 31.
|
Date:
3/17/2010
Project Status:
Concept plans (30%) are scheduled to be delivered on March 22.
|
Date:
3/2/2010
Project Status:
A plan development meeting is scheduled for March 8. Concept plans are scheduled to be delivered on March 22.
|
Date:
2/16/2010
Project Status:
The majority of the surveying has been completed. Topographic drawing is being prepared and design will start soon.
|
Date:
2/2/2010
Project Status:
CMT is continuing to work on surveying of the project.
|
Date:
1/19/2010
Project Status:
The design agreement with Crawford, Murphy, & Tilly was approved by Council. Surveying work will start this week.
|
Date:
1/5/2010
Project Status:
Engineering contract will go before Council at the January 14 meeting.
|
Date:
12/22/2009
Project Status:
Contract/scope negotiations are underway with the engineering firm.
|
Date:
11/20/2009
Project Status:
Discussed project with CMT (engineer) to resurrect for 2010.
|
Date:
9/29/2009
Project Status:
Amendment has been drafted for the County Road Board to forward fund project to start design in 2010.
|