Date:
8/31/2010
Project Status:
Storm sewer material bids were opened. Materials are expected to be delivered next week.
|
Date:
8/17/2010
Project Status:
Street Division continues construction of the project. Storm sewer materials are being re-bid.
|
Date:
8/4/2010
Project Status:
Street Division continues to work on curb and gutter installation on the west side of the road. Storm water materials for the project and being bid out.
|
Date:
7/20/2010
Project Status:
Curb and gutter work is underway.
|
Date:
7/6/2010
Project Status:
Roadway CL has been staked. City forces have begun construction on the project.
|
Date:
6/22/2010
Project Status:
Construction work on the project started last week. The surveyor will begin staking centerline of the roadway soon.
|
Date:
6/8/2010
Project Status:
Construction on Westridge Drive south of Montbrook Drive will begin on June 15.
|
Date:
5/25/2010
Project Status:
Easement acquisition continues. Construction on Westridge south of Montbrook will start when all easements from property owners south of Montbrook are acquired.
|
Date:
5/11/2010
Project Status:
Easement acquisition continues. 17 of 23 property owners have signed.
|
Date:
4/27/2010
Project Status:
16 of 23 parcels have signed.
|
Date:
4/13/2010
Project Status:
Funding for the project is in place. Continuing to acquire easements for the project. Construction on the project will not begin until all easements have been acquired.
|
Date:
3/30/2010
Project Status:
Continuing to work on easment acquisition. Still have 15 of 23 property owners.
|
Date:
3/17/2010
Project Status:
15 of 23 property owners have signed.
|
Date:
3/2/2010
Project Status:
Continuing to work on easement acquisition. Currently, 11 of 23 property owners have signed.
|
Date:
2/16/2010
Project Status:
Meeting with property owners to discuss project. Four of twenty-three property owners have signed easements.
|
Date:
2/2/2010
Project Status:
Plans have been delivered by the engineer. Easement acquisition letters have been sent to affected property owners.
|
Date:
1/19/2010
Project Status:
Plans are being revised based on City comments and will be delivered by the engineer next week.
|
Date:
1/5/2010
Project Status:
Plans are being revised by the engineer. ROW acquisition will begin once the ordinance is approved by Council.
|
Date:
12/22/2009
Project Status:
Final plan comments have been sent to the engineer. Plans are being revised. ROW and easement donations will be sought with final reading of the ordinance coming in early January.
|
Date:
12/8/2009
Project Status:
ROW and easements will be sought pending approval of Council.
|
Date:
11/10/2009
Project Status:
Plans are being reviewed.
|
Date:
10/20/2009
Project Status:
The engineer has finalized plans. City will review plans and provide comments to the designer.
|
Date:
9/18/2009
Project Status:
Engineer is continuing work on final plans.
|
Date:
7/15/2009
Project Status:
ROW plans have been submitted by the designer. Final plans are being developed.
|
Date:
5/29/2009
Project Status:
The City’s designer is working on ROW plans and final plans.
|
Date:
4/7/2009
Project Status:
The open house was held on March 24. Plans will move forward based on public comments from the hearing.
|
Date:
2/26/2009
Project Status:
Preliminary plans have been prepared. An open house style public hearing will be held at City Hall on March 24 from 4 p.m. until 6 p.m. Notification letters will be sent to nearby property owner on March 2. The public hearing will be advertised in the St. Charles Post on March 2.
|
Date:
12/12/2008
Project Status:
EFK Moen is under contract to perform the design of the project. Preliminary plans are expected the week of December 22.
|
Date:
7/29/2008
Project Status:
The City is negotiating a contract with a design firm.
|