Project Management

Project Details



Westridge Curb and Gutter

Name:  Westridge Curb and Gutter
Location:  Westridge Subdivision
Map:  
Contact Name:  Dan Buesse
Contact E-mail:  dbuesse@ofallon.mo.us
Contact Phone:  636-379-5492
Description:  Design of improvements to Westridge Parkway from I-70 Service Road between Bryan Road and Woodlawn to just north of Winston Place. These improvements would basically involve the design of curb and gutter along Westridge along with associated drainage improvements.

Status Reports


Date: 8/31/2010
Project Status: Storm sewer material bids were opened. Materials are expected to be delivered next week.

Date: 8/17/2010
Project Status: Street Division continues construction of the project. Storm sewer materials are being re-bid.

Date: 8/4/2010
Project Status: Street Division continues to work on curb and gutter installation on the west side of the road. Storm water materials for the project and being bid out.

Date: 7/20/2010
Project Status: Curb and gutter work is underway.

Date: 7/6/2010
Project Status: Roadway CL has been staked. City forces have begun construction on the project.

Date: 6/22/2010
Project Status: Construction work on the project started last week. The surveyor will begin staking centerline of the roadway soon.

Date: 6/8/2010
Project Status: Construction on Westridge Drive south of Montbrook Drive will begin on June 15.

Date: 5/25/2010
Project Status: Easement acquisition continues. Construction on Westridge south of Montbrook will start when all easements from property owners south of Montbrook are acquired.

Date: 5/11/2010
Project Status: Easement acquisition continues. 17 of 23 property owners have signed.

Date: 4/27/2010
Project Status: 16 of 23 parcels have signed.

Date: 4/13/2010
Project Status: Funding for the project is in place. Continuing to acquire easements for the project. Construction on the project will not begin until all easements have been acquired.

Date: 3/30/2010
Project Status: Continuing to work on easment acquisition. Still have 15 of 23 property owners.

Date: 3/17/2010
Project Status: 15 of 23 property owners have signed.

Date: 3/2/2010
Project Status: Continuing to work on easement acquisition. Currently, 11 of 23 property owners have signed.

Date: 2/16/2010
Project Status: Meeting with property owners to discuss project. Four of twenty-three property owners have signed easements.

Date: 2/2/2010
Project Status: Plans have been delivered by the engineer. Easement acquisition letters have been sent to affected property owners.

Date: 1/19/2010
Project Status: Plans are being revised based on City comments and will be delivered by the engineer next week.

Date: 1/5/2010
Project Status: Plans are being revised by the engineer. ROW acquisition will begin once the ordinance is approved by Council.

Date: 12/22/2009
Project Status: Final plan comments have been sent to the engineer. Plans are being revised. ROW and easement donations will be sought with final reading of the ordinance coming in early January.

Date: 12/8/2009
Project Status: ROW and easements will be sought pending approval of Council.

Date: 11/10/2009
Project Status: Plans are being reviewed.

Date: 10/20/2009
Project Status: The engineer has finalized plans. City will review plans and provide comments to the designer.

Date: 9/18/2009
Project Status: Engineer is continuing work on final plans.

Date: 7/15/2009
Project Status: ROW plans have been submitted by the designer. Final plans are being developed.

Date: 5/29/2009
Project Status: The City’s designer is working on ROW plans and final plans.

Date: 4/7/2009
Project Status: The open house was held on March 24. Plans will move forward based on public comments from the hearing.

Date: 2/26/2009
Project Status: Preliminary plans have been prepared. An open house style public hearing will be held at City Hall on March 24 from 4 p.m. until 6 p.m. Notification letters will be sent to nearby property owner on March 2. The public hearing will be advertised in the St. Charles Post on March 2.

Date: 12/12/2008
Project Status: EFK Moen is under contract to perform the design of the project. Preliminary plans are expected the week of December 22.

Date: 7/29/2008
Project Status: The City is negotiating a contract with a design firm.

RETURN TO PROJECT MANAGEMENT